Assam: ₹29.31 Lakh Expenditure For Unfinished Project Highlights Fiscal Irregularities

 

GUWAHATI: A recent investigation has unveiled glaring fiscal irregularities in Assam, underscoring the ineffective utilisation of ₹29.31 lakh in funds allocated for the construction of Bharat Nirman Rajiv Gandhi Sewa Kendra. Shockingly, the project remains incomplete despite the entire fund allocation having been disbursed.

The oversight of Executive Officer, Jugijan Anchalik Panchayat (AP) played a pivotal role in these financial mismanagements. The lack of adequate supervision regarding work execution and measurements resulted in a fictitious expenditure of ₹39.31 lakh.

In another disconcerting revelation, ₹27.04 lakh was disbursed for work that was valued at a mere ₹5.40 lakh. This fictitious payment of ₹21.64 lakh transpired due to erroneous decisions made by the Block Development Officer, Katlichera AP.

Moreover, questionable practices have been unearthed in the procurement of materials, which lacked a corresponding engagement of labour in the execution of pro-siltation works. This discrepancy is particularly pronounced in works valued at ₹2 crore in Morigaon district.

Furthermore, the reporting of work programmes was found to be inconsistent, raising significant doubts regarding the actual execution of these works. This revelation has prompted a comprehensive review of financial practices and a call for increased accountability in the allocation and execution of funds for various projects.